A punch list is created at what stage of the project?

Study for the Louisiana Contractor Business and Law Exam. Delve into flashcards and multiple choice questions, with hints and explanations for each. Prepare confidently for success!

A punch list is created during the completion stage of a construction project. This list serves as a detailed document that outlines tasks, corrections, or items that need to be finished before the project is considered fully complete. Typically, it is developed after substantial completion has been reached but before the final walkthrough or project closeout.

During this phase, the contractor and client or project owner walk through the project together to identify any unfinished work or deficiencies. The punch list ensures that all aspects of the project meet the agreed-upon specifications and quality standards before final payment is made and the project is officially closed. This process is crucial for ensuring that any issues are addressed to the satisfaction of all parties involved, reinforcing the importance of quality control and client satisfaction in the final stages of a project.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy